A novel multi criteria decision making model for optimizing time-cost-quality trade-off problems in construction projects

dc.contributor.authorMonghasemi, Shahryar
dc.contributor.authorNikoo, Mohammad Reza
dc.contributor.authorFasaee, Mohammad Ali Khaksar
dc.contributor.authorAdamowski, Jan
dc.date.accessioned2026-02-06T18:38:02Z
dc.date.issued2015
dc.departmentDoğu Akdeniz Üniversitesi
dc.description.abstractThe planning phase of every construction project is entangled with multiple and occasionally conflicting criteria which need to be optimized simultaneously. Multi-criterion decision-making (MCDM) approaches can aid decision-makers in selecting the most appropriate solution among numerous potential Pareto optimal solutions. An evidential reasoning (ER) approach was applied for the first time in the context of project scheduling to identify the best Pareto solution for discrete time-cost-quality trade-off problems (DTCQTPs). An exhaustive framework to synthesize the MCDM approaches with multi-objective optimization techniques was also proposed. To identify all global Pareto optimal solutions, a multi-objective genetic algorithm (MOGA) incorporating the NSGA-II procedure was developed and tested in a highway construction project case study. The Shannon's entropy technique served to determine the relative weights of the objectives according to their contributions to the uncertainty of the results obtained. A benchmark case study of DTCQTP was solved using the proposed methodology, and the Pareto optimal solutions obtained were subsequently ranked using the ER approach. By investigating the performance of each scheduling alternative based on multiple criteria (e.g., time, cost, and quality), the proposed approach proved effective in raising the efficiently of construction project scheduling. (C) 2014 Elsevier Ltd. All rights reserved.
dc.identifier.doi10.1016/j.eswa.2014.11.032
dc.identifier.endpage3104
dc.identifier.issn0957-4174
dc.identifier.issn1873-6793
dc.identifier.issue6
dc.identifier.orcid0000-0002-3740-4389
dc.identifier.orcid0000-0001-9436-0821
dc.identifier.scopus2-s2.0-84919807757
dc.identifier.scopusqualityQ1
dc.identifier.startpage3089
dc.identifier.urihttps://doi.org/10.1016/j.eswa.2014.11.032
dc.identifier.urihttps://hdl.handle.net/11129/12759
dc.identifier.volume42
dc.identifier.wosWOS:000349271500022
dc.identifier.wosqualityQ1
dc.indekslendigikaynakWeb of Science
dc.indekslendigikaynakScopus
dc.language.isoen
dc.publisherPergamon-Elsevier Science Ltd
dc.relation.ispartofExpert Systems With Applications
dc.relation.publicationcategoryMakale - Uluslararası Hakemli Dergi - Kurum Öğretim Elemanı
dc.rightsinfo:eu-repo/semantics/closedAccess
dc.snmzKA_WoS_20260204
dc.subjectDiscrete time-cost-quality trade-off
dc.subjectShannon's entropy
dc.subjectMulti-criterion decision-making
dc.subjectEvidential reasoning
dc.subjectMulti-objective optimization
dc.subjectNSGA-II
dc.subjectConstruction projects
dc.titleA novel multi criteria decision making model for optimizing time-cost-quality trade-off problems in construction projects
dc.typeArticle

Files